Herbert Hoover photo

Executive Order 5372—Power-Site Restoration No. 439, Oregon

June 20, 1930

Willamette Meridian

OWYHEE RIVER AND TRIBUTARIES

So much of the orders of May 24, 1909, creating Temporary Power-Site Withdrawal No. 3, and July 2, 1910, creating Power-Site Reserve No. 3, as modified by Order of Modification and Restoration No. 203 approved February 15, 1916, and by Order of Modification and Restoration No. 287 approved August 29, 1919, as affects the lands hereinafter described, is hereby revoked:

T. 27 S.,  R. 41  E., sec  36,  NW. ¼  of NE. ¼, NW. ¼, W. ½ of SW. ¼;

T. 26 S.,  R. 43  E., sec.  13,  lots 1,  2, 3, and  4;

T. 23 S.,  R. 44  E., sec.  17,  SE. ¼ of SE. ¼

sec.  20,  lots 2, 3, 6, and  7;

sec. 29, lot 2;

T. 25 S., R. 44 E., sec, 15, lots 1, 4, 5, 6, 7, 8, and 9.

JOHN DAY RIVER

So much of the orders of June 26, 1909, creating Temporary Power-Site Withdrawal No. 24, and July 2, 1910, creating Power-Site Reserve No. 24, as affects the lands hereinafter described, is hereby revoked:

T. 3 S.,  R.  18  E., sec.  35,  S. ½ of SW. ¼

T. 4 S.,  R.  18  E., sec.  2, lots  3  and 4 of  NW. ¼

T. 6 S.,  R.  19  E., sec.  31,  E.  ½  of E. ½;

T. 7 S.,  R.  19  E., sec.  18,  E.  ½  of NE. ¼,  NE. ¼ of SE. ¼;

T. 8 S., R. 19 E., sec. 3, lot 5;

sec. 10, NW. ¼ of SW. ¼

sec. 26, E. ½ of NE. ¼

T. 1 S., R. 20 E., sec. 7, NW. ¼ of SW. ¼

T. 9 S., R. 22 E., sec. 22, SE. ¼ of SW. ¼;

sec. 23, NE. ¼ of NW. ¼;

sec. 28, SW. ¼ of NE. ¼, NW. ¼ of SE. ¼

sec. 32, S. ½ of SW. ¼;

T. 9 S., R. 23 E., sec, 8, E. ½ of SW. ¼, NW. ¼ of SE. ¼;

sec. 18, lots 3 and 4 of SW. ¼, NE. ¼ of NE. ¼

T. 9 S., R. 25 E., sec. 25, W. ½ of NE. ¼, NE. ¼ of NW. ¼.

DESCHUTES RIVER

So much of the orders of June 30, 1909, creating Temporary Power-Site Withdrawal No. 26, and July 2, 1910, creating Power-Site Reserve No. 26, as affects the lands hereinafter described, is hereby revoked:

T. 13 S., R. 12 E., sec. 20, NE. ¼ of SE. ¼;

T. 14 S., R. 12 E., sec. 9, SE. ¼ of NE. ¼;

sec, 26, SE. ¼ of NW. ¼;

T. 15 S., R. 12 E., sec. 1, E. ½ of SW. ¼;

sec. 11, E. ½ of NE. ¼

sec. 12, NW. ¼ of NW. ¼

sec. 26, NE. ¼ of SE. ¼

T. 3 S., R. 14 E., sec. 23, SW. ¼ of SW. ¼;

sec. 26, W. ½ of NW. ¼ NW. ¼ of SW. ¼;

T. 8 S., R. 14 E., sec. 9, lot 5;

sec. 15, lots 1, 2, and 3;

T. 2 S., R. 15 E., sec. 13, SE. ¼ of SE. ¼;

sec. 24, NE. ¼ of NE. ¼;

T. 1 S., R. 16 E., sec. 20, SW. ¼ of NE. ¼, SE. ¼ of NW. ¼, NE. ¼ of SW. ¼;

. T. 2 S., R. 16 E., sec. 18, lot 4 of SW. ¼.

UPPER DESCHUTES RIVER

So much of the orders of November 20, 1909, creating Temporary Power-Site Withdrawal No. 68, and July 2, 1910, creating Power-Site Reserve No. 68, as affects the lands hereinafter described, is hereby revoked:

T. 18 S., R. 11 E., sec. 27, NW. ¼ of SW. ¼

NEHALEM RIVER

So much of the orders of December 18, 1909, creating Temporary Power-Site Withdrawal No. 89, and July 2, 1910, creating Power-Site Reserve No. 89, as affects the lands hereinafter described, is hereby revoked:

T. 4 N., R. 8 W., sec. 25, lots 2, 3, and 4.

WALLA WALLA RIVER

So much of the orders of January 20, 1910, creating Temporary Power-Site Withdrawal No. 108, and July 2, 1910, creating Power-Site Reserve No. 108, as affects the lands hereinafter described, is hereby revoked:

T. 4 N., R. 37 E., sec. 9, E. ½ of NW. ¼;

sec. 10, NW. ¼ of SE. ¼;

sec. 15, SE. ¼ of NE. ¼;

T. 5 N., R. 37 E., sec. 27, W. ½ of NE. ¼, SE. ¼ of NE. ¼

HOOD RIVER

So much of the orders of February 28, 1910, creating Temporary Power-Site Withdrawal No. 118, and July 2, 1910, creating Power-Site Reserve No. 118, as affects the lands hereinafter described, is hereby revoked:

T. 1 S., R. 10 E., sec. 4, SW. ¼ of SW. ¼

sec. 9, W. ½ of NW. ¼, NW. ¼ of SW. ¼;

sec. 17, E. ½ of SE. ¼;

sec. 20, E. ½ of NE. ¼, SE. ¼ of SW. ¼, N. ½ of SE. ¼, SW. ¼ of SE. ¼;

sec. 21, NW. ¼;

sec. 29, N. ½ of NE. ¼, SW. ¼ of NE. ¼, NE. ¼ of NW. ¼, S. ½ of NW. ¼, W. ½ of SE. ¼

DESCHUTES RIVER NO. 2

So much of the orders of March 18, 1910, creating Temporary Power-Site Withdrawal No. 125, and July 2, 1910, creating Power-Site Reserve No. 125, as modified by Order of Modification approved February 21, 1913, as affects the lands hereinafter described, is hereby revoked:

T. 3 S., R. 14 E., sec. 35, N. ½ of SW. ¼.

MALHEUR RIVER

So much of the order of February 28, 1911, creating Power-Site Reserve No. 175, as affects the lands hereinafter described, is hereby revoked:

T. 20 S., R. 37 E., sec. 27, SE. ¼ of NE. ¼, NE. ¼ of SE. ¼;

T. 21 S., R. 40 E., sec. 2, lot 4.

DONNER AND BLITZEN RIVER

So much of the order of October 30, 1911, creating Power-Site Reserve No. 220, as modified by Order of Modification and Restoration No. 136 approved April 16, 1914, as affects the lands hereinafter described, is hereby revoked:

T. 33 S., R. 32½ E., sec. 36, W. ½ of NW. ¼, SE. ¼ of NW. ¼, SW. ¼.

MALHEUR RIVER NO. 2

So much of the order of April 16, 1912, creating Power-Site Reserve No. 260, as affects the lands hereinafter described, is hereby revoked:

T. 21 S., R. 38 E., sec. 9, SE. ¼ of SE. ¼

sec. 10, SW. ¼ of NW. ¼, W. ½ of SW. ¼

T. 21 S., R. 40 E., sec. 2, lot 3;

sec. 3, lots 1, 2, 3, and 4, S. ½ of NE. ¼, SE. ¼ of NW. ¼;

sec. 4, lot 1.

DEEP CREEK

So much of the order of April 29, 1912, creating Power-Site Reserve No. 265, as modified by Order of Modification and Restoration No. 311 approved October 4, 1921, as affects the lands hereinafter described, is hereby revoked:

T. 40 S., R. 22 E., sec. 8, SW. ¼ of SW. ¼;

sec. 9, SW. ¼ of SE. ¼;

T. 39 S., R. 23 E., sec. 14, SE. ¼ of SW. ¼, SW. ¼ of SE. ¼.

DESCHUTES RIVER

So much of the order of September 23, 1912, creating Power-Site Reserve No. 288, as affects the lands hereinafter described, is hereby revoked:

T. 14 S., R. 12 E, sec. 26, SW. ¼ of NW. ¼, NW. ¼ of SW. ¼.

CHEWAUCAN RIVER NO. 2

So much of the order of December 14, 1912, creating Power-Site Reserve No. 323, as affects the lands hereinafter described, is hereby revoked:

T. 34 S., R. 18 E., sec. 4, lots 2, 3, and 9.

DESCHUTES RIVER NO. 4

So much of the order of January 27, 1913, creating Power-Site Reserve No. 334, as affects the lands hereinafter described, is hereby revoked:

T. 19 S., R. 11 E., sec. 4, lot 3.

DONNER AND BLITZEN RIVER AND TRIBUTARIES

So much, of the order of March 17, 1913, creating Power-Site Reserve No. 344, as modified by Order of Modification approved May 19, 1913, as affects the lands hereinafter described, is hereby revoked:

T. 30 S., R. 33 E., sec. 10, S. ½ of SE. ¼;

sec. 23, SE. ¼ of SE. ¼;

T. 31 S., R. 33 E., sec. 11, lots 5 and 8; sec. 14, lot 1;

T. 31 S., R. 34 E., sec. 6, lots 3 and 4, SE. ¼ of NW. ¼

sec. 30, lot 4, E. ½ of SW. ¼

sec. 31, lots 1 and 2.

CROOKED RIVER

So much of the order of March 9, 1914, creating Power-Site Reserve No. 425, as modified by Order of Modification approved February 10, 1916, as affects the lands hereinafter described, is hereby revoked:

T. 12 S., R. 12 E., sec. 33, SW. ¼ of NE. ¼

T. 13 S., R. 12 E., sec. 3, lot 9;

sec. 4, lots 2 and 6, SE. ¼ of NW. ¼, SW. ¼ of SE. ¼

sec. 10, NE. ¼ of NE. ¼, S. ½ of NE. ¼, NE. ¼ of NW. ¼, N. ½ of SE. ¼, SE. ¼ of SE. ¼;

sec. 13, lot 13;

sec. 14, lots 3, 6, and 12, NW. ¼ of NW. ¼, S. ½ of NW. ¼

SOUTH FORK OF WALLA WALLA RIVER

So much of the order of January 14, 1915, creating Power-Site Reserve No. 477, as affects the lands hereinafter described, is hereby revoked:

T. 4 N., R. 37 E., sec. 5, E. ½ of SE. ¼

T. 5 N., R. 37 E., sec. 31, NW. ¼ of SE. ¼, SE. ¼ of SE. ¼.

SANDY RIVER

So much of the order of August 2, 1916, creating Power-Site Reserve No. 537, as affects the lands hereinafter described, is hereby revoked:

T. 2 S., R. 5 E., sec. 17, NE. ¼

DESCHUTES RIVER

So much of the order of October 30, 1916, creating Power-Site Reserve No. 561, as affects the lands hereinafter described, is hereby revoked:

T. 1 S., R. 16 E., sec. 17, W. ½ of NE. ¼, SE. ¼ of NW. ¼ NE. ¼ of SW. ¼, NW. ¼ of SE. ¼.

SPENCER CREEK

So much of the orders of January 19, 1917, creating Water Power Designation No. 3, and January 19, 1917, creating Power-Site Reserve No. 581, as affects the lands hereinafter described, is hereby revoked:

T. 38 S., R. 5 E., sec. 13, lot 3.

CITY OF BAKER, WATER-SUPPLY CONDUIT

So much of the order of March 21, 1917, creating Power-Site Reserve No. 591, as modified by Order of Modification approved December 3, 1918, as affects the lands hereinafter described, is hereby revoked:

T. 9 S., R. 40 E., sec. 19, SE. ¼ of SW. ¼

. sec. 30, N. ½ of NW. ¼

ILLINOIS RIVER

So much of the orders of April 27, 1917, creating Water Power Designation No. 10, and April 28, 1917, creating Power-Site Reserve No. 618, as affects the lands hereinafter described, is hereby revoked:

T. 39 S., R. 8 W., sec. 5, SE. ¼ of NE. ¼, SW. ¼ of SE. ¼;

sec. 9, lot. 3, NE. ¼ of NE. ¼, SW. ¼ of NW. ¼, W. ½ of SW. ¼

sec. 21, SE. ¼ of NW. ¼

T. 35 S., R. 11 W., sec. 29, lots 1 and 2.

ROGUE RIVER

So much of the orders of April 27, 1917, creating Water Power Designation No. 10, and April 28, 1917, creating Power-Site Reserve No. 621, as affects the lands hereinafter described, is hereby revoked:

T. 35 S., R. 7 W., sec. 11, lot 3;

T. 34 S., R. 11 W., sec. 17, lot 2.

UMPQUA RIVER

So much of the orders of July 13, 1917, creating Water Power Designation No. 11, and July 24, 1917, creating Power-Site Reserve No. 633, as affects the lands hereinafter described, is hereby revoked:

T. 22 S., R. 7 W., sec. 17, SW. ¼ of SW. ¼.

COAST STREAMS IN WESTERN OREGON

UMPQUA RIVER BASIN

So much of the orders of July 13, 1917, creating Water Power Designation No. 11, and December 12, 1917, creating Power-Site Reserve No. 659, as affects the lands hereinafter described, is hereby revoked:

T. 30 S., R. 4 W., sec. 15, lot 10.

WILLAMETTE RIVER TRIBUTARIES

SANTIAM RIVER BASIN

So much of the orders of December 12, 1917, creating Water Power Designation No. 14, and December 12, 1917, creating Power-Site Reserve No. 661, as affects the lands hereinafter described, is hereby revoked:

T. 9 S., R. 3 E., sec. 17, NW. ¼ of NW. ¼.

COAST STREAMS IN WESTERN OREGON

NESTUCCA RIVER BASIN

TRASK RIVER BASIN

ALSEA RIVER BASIN

So much of the order of December 12, 1917, creating Power-Site Reserve No. 662, as affects the lands hereinafter described, is hereby revoked:

T. 3 S., R. 7 W., sec. 26, N. ½ of SW. ¼, SW. ¼ of SW. ¼

sec. 28, lots 2, 3, and 4, SW. ¼ of SE. ¼

T. 1 S., R. 8 W., sec. 27, NW. ¼ of SW. ¼;

sec. 28, SE. ¼ of NE. ¼, N. ½ of SE. ¼;

T. 14 S., R. 9 W., sec. 5, lots 7 and 8.

SANTIAM RIVER

So much of the order of December 12,1917, creating Power-Site Reserve No. 672, as affects the lands hereinafter described, is hereby revoked:

T. 12 S., R. 4 E., sec. 19, lot 5.

CLACKAMAS RIVER

So much of the order of April 24, 1918, creating Power-Site Reserve No. 680, as affects the lands hereinafter described, is hereby revoked:

T. 4 S., R. 5 E., sec. 27, S. ½ of NW. ¼, N. ½ of SW. ¼, SW. ¼ of SW. ¼

sec. 28, SE. ¼ of NE. ¼, S. ½;

sec. 29, S. ½;

sec. 32, NE. ¼, N. ½ of NW. ¼, SE. ¼ of NW. ¼ N. ½ of SE. ¼

sec. 33, lots 1 and 2 of SW. ¼, SW. ¼ of NW. ¼, N. ½ of SW. ¼.

COLUMBIA RIVER

So much of the order of June 2, 1920, creating Power-Site Reserve No. 742, as affects the lands hereinafter described, is hereby revoked:

T. 5 N., R. 30 E., sec. 5, lots 2, 3, 4, and 5;

sec. 6, lot 3;

sec. 7, S. ½ of lots 1 and 2 of SW. ¼;

T. 6 N., R. 30 E., sec. 33, lots 2, 3, and 4;

sec. 34, lots 1, 2, and 3.

DEEP CREEK BASIN

So much of the order of November 24, 1922, creating Power-Site Classification No. 51, Oregon No. 5, as affects the lands hereinafter described, is hereby revoked:

T. 30½ S., R. 34 E., sec. 29, lots 3 and 4, S. ½ of NW. ¼, S. ½;

sec. 30, SE. ¼ of NE. ¼.

Signature of Herbert Hoover
HERBERT HOOVER

The White House,
June 20, 1930.

Herbert Hoover, Executive Order 5372—Power-Site Restoration No. 439, Oregon Online by Gerhard Peters and John T. Woolley, The American Presidency Project https://www.presidency.ucsb.edu/node/361157

Simple Search of Our Archives